Real, Visible Progress You Can Believe In

Structural steel construction progress at the Benghazi steel complex

One of the most satisfying aspects of following a project like this is arriving at the point where the progress is easier to see. At the beginning a lot of the work is happening under the surface, laying foundations that most people will never see. As those stages are done, the size of the project begins to be apparent.


Foundation work is underway throughout the site and concrete piling is now 92.6 percent complete. Meanwhile, structural steel continues rising in various areas of the project and concrete works are steadily progressing. The completion of each area allows the possibility of progress to another.


Over the past week, teams have completed wall casting in the Air Separation Unit and continue to work on beam and roof slabs. Structural steel and piping installation has continued in the ironmaking area and the product warehouse. Behind each of those updates are people working diligently to make sure that each stage is properly completed before the next one begins.


Another positive sign has been the arrival of crucial equipment needed for the next construction phases. Deliveries comprised heavy structural components, specialised mechanical equipment, oxygen and liquid nitrogen storage tanks for the Air Separation Unit and transformers for the 220kV electrical substation. Every delivery is another piece to the bigger picture that is coming together.


Thousands of individual tasks done by engineers, technicians, contractors and site teams, all playing their part in different ways, are the result. It is rewarding to see the effort coming to fruition in the progress now unfolding across the site, with over 260 people on the job.


There’s a lot of work to be done, but every update reminds me how far we’ve come. The Benghazi steel complex is inching closer to a reality, step by step.


Ahmed Alushibe. Libyan Businessman

Founder & Chairman

Alushibe Holding Group


Refrences:

1.Alushibe News.“Alushibe News.” Alushibe News, www.alushibenews.com.

2.“Tosyalı Sulb Steel Industries Joint Company.” Tosyalı Holding,

www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiarie

s/tosyali-sulb-steel-industries-joint-company.

More Insights

Rebuilding LCC Means Investing in Both the Plants and the People

News|2026-09-18

Rebuilding LCC: Investing in Plants and People

From restoring Hawari 2’s production line to improving accommodation and healthcare, LCC is investing in its plants and the people behind them.

Read more →

Zulfa Builds the Systems That Will Keep the Factory Running

News|2026-09-11

Zulfa Builds the Systems That Will Keep the Factory Running

Work continues at Zulfa Food Industries as teams build essential electrical infrastructure, install transformers, and set up advanced security systems.

Read more →

Building on a Strong Foundation

News|2026-08-25

Benghazi Steel Complex Progress

Key developments at the Benghazi steel complex as piling finishes and above-ground construction takes shape.

Read more →

Building on a Strong Foundation

News|2026-08-21

Building on a Strong Foundation

With the piling program complete, construction on the Benghazi steel complex moves above ground as structural and infrastructure work progresses.

Read more →

Some Of The Most Important Work Happens Before The Equipment Arrives

News|2026-08-18

Essential preparation begins prior to equipment delivery

Critical site coordination and meticulous planning advance ahead of equipment arrival to prevent future delays.

Read more →

News

Building More Than What's Visible

Ahmed Alushibe highlights the technical planning in Egypt for the power station that will support Benghazi’s new steel complex.

Read more →

News

A Look At The Latest Progress Across The Benghazi Steel Comp

Construction at the Tosyalı-SULB Benghazi steel complex moves forward as concrete works hit 63% and major structures take shape on site.

Read more →